Setup LED lights for train:
Objectives of the project:
Replace fluorescent lamps with new technology LED lights.
Reduce power consumption.
Beautification .
Reduce service and replace cost.
Geographical location of the project:
Tehran, Iran
Customer:
RAJA.
Main contractor:
Pardazesh Tamkar Eng Co.
Project Implementation Activities:
Design led lights for passenger room and hall.
Obtain necessary standards.
Produce LED lights.
Key layout times:
Date of Contract Entry: Aug 27, 2012
Sample design 25 days
Verification test 15 days
Production 32 days